You do not have to move out
When a house needs new wiring throughout, the first worry is almost never the work. It is logistics. Where do we sleep, does the fridge stay running, is the house torn open for a month, can the kids use their rooms. Those are the right questions, and the answer is that a rewire on an occupied house is done in phases precisely so the family never loses the house.
It takes longer that way than it would on an empty building. That is the trade, and almost everybody takes it.
Why the houses up here are the way they are
A lot of what I rewire in this part of Navajo County grew by addition. Somebody built a cabin, then closed in a porch, then put a bedroom on the back, then finished a garage, over thirty or forty years and often with different hands on each piece. The wiring reflects that history exactly.
What that produces is specific and recognizable. Circuits that cross between the original structure and an addition for no reason anyone remembers. A subpanel fed from a circuit that should never have fed a subpanel. Three generations of wiring method meeting in one junction box. Splices in places with no box at all, because when that addition went up nobody was coming to look. Knob and tube surviving in one wall of the original cabin while everything around it was replaced.
This is why a rewire here is harder to scope than one on a tract house of a known vintage. I do not fully know what is in the walls until the walls are open, and I will say so up front rather than pretending otherwise and billing the surprise later.
Show Low, Linden and Lakeside are all full of houses built this way, which is why a rewire in Show Low is rarely a matter of pulling the same cable through the same kind of wall twice.
Phase order: how I usually break it up
The sequence varies by house, but the logic behind it rarely does. The idea is that at the end of each phase the house works, and nothing is left half done overnight.
Bedrooms and living areas tend to go first. They are the easiest rooms to do without displacing anybody, because you can move a family out of two bedrooms for a few days when they have the rest of the house. They also tend to hold the oldest and least adequate wiring, so there is real safety gained early.
The kitchen is its own phase and the most disruptive one, because it needs several dedicated circuits, the counter receptacles have to land on the required spacing with ground fault protection, and appliances come out to get behind them. I like to do the kitchen when the rest of the house is already on new wiring, so the temporary circuits I need are coming from somewhere solid.
Baths and laundry are usually bundled with or just after the kitchen, same reasons and same required devices.
The panel and the service either lead the whole project or follow the first phase, and which one depends on whether the existing panel can safely host new circuits while the work goes on. If it cannot, it goes first and everything else lands in new gear. If it can, I would often rather do the panel after the branch circuit count is settled.
Garage, outbuildings and exterior go last. They are the least painful to live without.
What gets opened and what gets fished
The plain answer is that you cannot rewire a house without opening some walls, and the goal is to open as few as possible in places that are cheap to close.
A great deal of the work gets fished: new cable pulled through existing stud bays from an attic above or a crawl space below, without touching the drywall in between. Where a house has accessible space on both ends, fishing does most of it.
Openings happen at the places where that fails. Fire blocking in a stud bay stops a fish cold. Insulation packed tight in an exterior wall does the same. A second story with a finished ceiling under it and no attic access over it. Balloon framing in an older structure, which is a different problem and sometimes an easier one. In those spots I cut a patch, do the work, and the patch gets closed and finished afterward.
Whether patching and paint are in my scope or yours is a thing to settle explicitly before the first day, because assuming it either way is how a project ends badly.
Living in it, practically
A few things that make it tolerable, learned from doing it.
- The refrigerator stays running. It gets a temporary circuit from something already converted, and it does not get moved around.
- Work happens in daylight hours and the house is on by evening. Dust gets contained with plastic at the phase boundary.
- Pick the season deliberately. Opening exterior walls in January up here is a bad idea, and so is doing it during monsoon season if the roof is involved. Late spring and early fall are the windows.
- Expect to move furniture out of the active rooms yourself, or say so and have it included.
- If the house is a second home, the whole calculation changes and it is usually better to do it in one push while nobody is there.
The mistake that costs the most
Closing a wall before the inspector sees it.
A rewire is permitted work, and there is a rough inspection that happens with the cable run, the boxes set, and everything visible, before any drywall goes back. The inspector is looking at things that stop being visible once a wall is closed: cable support and stapling, the nail plates protecting cable where it passes through framing, box fill, how the grounds are made up, how the cable enters each box, the fire blocking and sealing where penetrations happen.
If a wall gets closed before that happens, the only road forward is opening it again. That is drywall, mud, tape, texture, and paint, twice, on work that was probably fine. Weeks get lost to it, usually because somebody was enthusiastic about getting a room back.
So the rule on my jobs is that nothing closes without the rough signed off, and I would rather a homeowner be annoyed at me for a week than pay to open a finished wall. The final inspection comes after the devices and the cover plates are in, and that one is comparatively quick.
What you get for it, besides safety
Safety is the reason people start. It is worth naming what else lands, because it is a substantial list and it is the part that makes the project feel worth the disruption afterward.
Enough circuits that a space heater and a hair dryer are not a problem. Receptacles where the code wants them, which in older rooms means roughly twice as many as you have and no extension cords running under rugs. Grounded outlets throughout, which means surge protection actually works and a three-prong plug is honest about what is behind it. Arc fault and ground fault protection where it belongs. A panel with a real directory and room left in it for whatever you add in ten years. And a documented, permitted record of the work, which matters a great deal when the house sells and a buyer’s inspector goes looking.
On a seasonal property there is one more: the wiring stops being a thing you worry about in March when you drive up and open the place.
Before any of this gets priced
Before any of this gets priced I want to see the panel, get into the attic and the crawl space, pull a couple of devices to see what wiring method and what grounding actually exist, and find out how the additions were tied in. That visit is also where the phasing gets drawn up around your family rather than around my convenience.
A rewire is a long job and you will be living inside it, so the walkthrough matters more than the phone call. Call (928) 358-2546 or outline the house on the contact page and we will come walk it with you.